Project Description:
The objective of this project was river engineering and constructive implementation planning for the reservoir (length 1.7km) and the underwater recess (length 1.9 km) of the Salzach power plant Werfen – Pfarrwerfen with a capacity of 14.9 MW. Pier underpinnings and extensive safety measures for the lateral drainage slopes are planned for the underwater recess, in the reservoir, all of the seals – water retention in the back-land. Extensive collaboration with aquatic ecology. Final hydraulic calculation of the entire measure.

Client:
Salzburg AG
Timeframe: 2006 - 2009
Project Share WERNER CONSULT: Implementation planning