Project Description:
The Bruck tunnel chain underwent a full restoration after more than 18 years of use. The Tanzenberg tunnel with 2.5 km length and 2 parallel pipes, as well as the central monitoring center Bruck have been upgraded to the newest level of technology. This project was primarily focused on the ventilation system, the electric-mechanical equipment, the communication system, video monitoring equipment as well as the new operating station and rescue- and evacuation routes.
Client: ASFiNAG Bau Management GmbH
Timeframe: 2007 - 2009
Construction Term: 2007 - 2009
Project Share WERNER CONSULT in consortium:
Support management during the planning- and tender phase
Project Description:
As the final section, the gap closure of S 36 Murtal Schnellstraße (speedway)was planned in the area between Judenburg and St. Georgen o. J.
Client: ASFiNAG Bau Management GmbH / Styria Provincial Government
Timeframe: 2005 - 2011
Construction Term: open ended
Project Share WERNER CONSULT:
Route studies
Permit application project (road planning, bridges, legal procedures, UVP)
Project Description:
S 8 Marchfeld Schnellstraße (speedway) represents a high-ranking road connection running diagonally through the Marchfeld north of the Donau from Vienna in the area of S 1 Vienne Außenring Schnellstraße (outer perimeter speedway) and Slovakia north of Bratislava
Client: ASFINAG Bau Management GmbH
Timeframe: 2007 - 2018
Construction Term: 2015 - 2018
Project Share WERNER CONSULT in consortium:
Project control (preliminary project, permit application project, construction project optional)
Project Description:
L 303 was completely restructured on a 2.5 km long section coming from St. Andrä im Sausal, the, track support and super-structure has been replaced as well as the drainage system and entrances/exits have been adapted.
Client: Styria Provincial Government
Timeframe: 2010
Construction Term: 2011
Project Share WERNER CONSULT:
Construction project, road planning
Project Description:
L 303 was completely restructured at a 2.5 km long section coming from St. Andrä im Sausal, the, track support and super-structure has been replaced as well as the drainage system and entrances/exits have been adapted.
Client: Styria Provincial Government
Timeframe: 2011 - 2012
Timeframe: 2012 - 2013
Project Share WERNER CONSULT:
Construction project (road planning, legal procedures)